Question: PROJECT 2 : Scheduling and Duration A project is made up of five activities: A through E . The project team has decided to weigh
PROJECT : Scheduling and Duration
A project is made up of five activities: A through E The project team has decided to weigh duration estimates from three different sources as follows: Optimistic Likely and Pessimistic
Calculate the expected DURATION for each Activity
Activities Optimistic Likely Pessimistic Expected
A
B
C
D
E
Optimistic
Likely
Pessimistic
Use the activity schedule below and the activity durations you have calculated to fill in the chart at the bottom of the page.