Question: PROJECT 2 : Scheduling and Duration A project is made up of five activities: A through E . The project team has decided to weigh

PROJECT 2: Scheduling and Duration
A project is made up of five activities: A through E. The project team has decided to weigh duration estimates from three different sources as follows: Optimistic 2/6, Likely 3/6 and Pessimistic 1/6.
Calculate the expected DURATION for each Activity
Activities Optimistic Likely Pessimistic Expected
A 81220
B 248
C 111
D 4810
E 235
Optimistic 2/6
Likely 3/6
Pessimistic 1/6
Use the activity schedule below and the activity durations you have calculated to fill in the chart at the bottom of the page.