Question: Project A is expected to lead to a productivity increase of $700K. The probability for the project to succeed is 60%. If the project fails,
Project A is expected to lead to a productivity increase of $700K. The probability for the project to succeed is 60%. If the project fails, there will be a loss of $200K. What is the expected value of Project A.