Question: Project A Project B Time 0 - 10,000 - 10,000 Time 1 5,000 4,000 Time 2 4,000 3,000 Time 3 3.000 10,000 If WiseGuy Inc.

 Project A Project B Time 0 - 10,000 - 10,000 Time

Project A Project B Time 0 - 10,000 - 10,000 Time 1 5,000 4,000 Time 2 4,000 3,000 Time 3 3.000 10,000 If WiseGuy Inc. is choosing one of the above mutually exclusive projects (Project A or Project B). given a discount rate of 7%, which should the company choose? O Project A O Project B O Neither project -- both have negative NPV