Question: Project A req return 0.12 1 2 3 4 5 FCF -2,100 350 700 800 750 525 Project B req return 0.105 1 2 3

Project A
req return 0.12
1 2 3 4 5
FCF -2,100 350 700 800 750 525
Project B
req return 0.105
1 2 3 4 5 6
FCF -100,000 -15000 15000 25000 35000 45000 55000

1. What is the NPV for Project A? (to the nearest cent)

2. What is the IRR for Project A? (Remember to use decimals and not answer in percents for all questions asking for interest rates.)

3. What is the Profitability Index for Project A? (to the second decimal place)

4. What is the Payback period for Project A?

7. What is the NPV for Project B? (To the nearest cent.)

8. What is the IRR for Project B? (Remember to not use percents.)

9. What is the Profitability Index for Project B? (To the second decimal place.)

10. What is the Payback period for Project B?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!