Question: Project A YEAR 0 1 2 3 4 Expected CFs ($) -1,000,000 50,000 200,000 600,000 1,000,000 Project B YEAR 0 1 2 3 4 Expected
Project A
YEAR 0 1 2 3 4
Expected CFs ($) -1,000,000 50,000 200,000 600,000 1,000,000
Project B
YEAR 0 1 2 3 4
Expected CFs ($) -900,000 650,000 650,000 550,000300,000
Find the: Payback period, Discounted payback period, NPV, IRR, and Profitability Index.
My answers:
Project A B Rank A Rank B
PBP 3.15 1.38 2 1
Did PBP 3.98 1.79 2 1
NPV $612,847 $596,206 1 2
IRR 35.93%55.07% 2 1
PI 1.61 1.66 2 1
Can somebody show me where I am going wrong? Thank you