Question: Project Activity Q has two immediate predecessors, Activity H and Activity K. Activity H's Early Finish (EF) is equal to 23 and Activity K's EF

Project Activity Q has two immediate predecessors, Activity H and Activity K. Activity H's Early Finish (EF) is equal to 23 and Activity K's EF is equal to 25. If Activity Q's duration is 6, what is Q's EF?

Please show workProject Activity Q has two immediate

Question 2 0/3 pts Project Activity Q has two immediate predecessors, Activity Hand Activity K. Activity H's Early Finish (EF) is equal to 23 and Activity K's EF is equal to 25. If Activity Q's duration is 6, what is Q's EF? 31