Question: Project Activity Q has two immediate predecessors, Activity H and Activity K. Activity H's Early Finish (EF) is equal to 23 and Activity K's EF
Project Activity Q has two immediate predecessors, Activity H and Activity K. Activity H's Early Finish (EF) is equal to 23 and Activity K's EF is equal to 25. If Activity Q's duration is 6, what is Q's EF?
Please show work