Question: project completion time and the critical path should also be determined. Here are the activity times: table [ [ Activity , Time ( weeks

project completion time and the critical path should also be determined. Here are the activity times:
\table[[Activity,Time (weeks),Immediate Predecessor(s),Activity,Time (weeks) Immediate Predecessor(s)],[A,6,-,E,5,B],[B,6,-,F,5,B],[C,3,A,G,11,C, E],[D,1,A,H,6,D, F]]
Dave's earliest start (ES) and earliest finish (EF) are:
\table[[Activity,ES,EF],[A,,6],[B,0,],[C,,9],[D,6,],[E,,11],[F,6,],[G,,22],[H,,17]]
Dave's latest start (LS) and latest finish (LF) are:
\table[[Activity,LS,LF],[H,16,
 project completion time and the critical path should also be determined.