Question:
Project | Cost | NPV |
---|---|---|
A | $1,061,191 | $122,737 |
B | 561,758 | 58,102 |
C | 1,647,849 | 280,660 |
D | 1,026,020 | 89,365 |
E | 191,870 | 17,568 |
F | 1,333,625 | 76,960 |
G | 3,102,642 | 123,240 |
H | 275,568 | 79,367 |
I | 2,044,070 | 60,506 |
J | 1,017,567 | 56,690 |
- • You have been asked to choose which investments should be made.
- • Using the Solver, determine which of the above projects should be included in the budget if the firm's goal is to maximize shareholder wealth (Note: Set the Solver to use the Simplex LP method, and turn off the Ignore Integer Constraints setting.)