Question: Project Cost Use WBS activity costs provided ( see Excel ) to calculate total project cost. Project overhead is 2 5 % of total WBS

Project Cost
Use WBS activity costs provided (see Excel) to calculate total project cost. Project overhead is 25% of total WBS activity cost. Show cost with and without overhead costs.
Project NPV
Given the provided 5 year cash inflows (see Excel) calculate the project NPV. The discount rate will be 8% for the project. Show the project NPV with and without overhead (i.e. you need to calculate NPV using WBS costs first, then recalculate NPV after you add-in overhead). However, your recommendation should be based on total project cost (WBS activity cost + overhead). Provide a recommendation to approve / reject the project ... include your rationale
Include screenshots of your NPV calculations.
Remember that the initial investment (outflow) for NPV calculation is total WBS costs then recalculate NPV using total WBS costs + Overhead
Activity Cost
WBS Item
R&D Project Development
Need Survey $ 95,000
Set Product Specs $ 57,600
Shelf life Report $ 19,200
Nutrition Report $ 15,000
Select Fruit Suppliers $ 15,000
Initial Production
Equipment Rehab $ 400,000
Production Trials $ 235,200
Quality Trials $ 125,000
Quality Metrics $ 7,000
Quality Training $ 200,000
Distribution
Market Testing $ 80,000
Package Design $ 31,000
Select Distributors $ 80,000
Legal
Complete FDA Certification $ 60,000
Register Trademark $ 14,400
Prepare Product Launch $ 268,800
Overhead =25% total cost of WBS activities
Cash Flows for NPV
Year 1 Year 2 Year 3 Year 4 Year 5
$ 575,000 $ 575,000 $ 575,000 $ 575,000 $ 575,000
DISCOUNT RATE: 8%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!