Question: Project crashing is the method for ------------- Adding duration to each activity Adding resources at critical points Shortening the project duration by reducing the time
Project crashing is the method for -------------
| Adding duration to each activity | ||
| Adding resources at critical points | ||
| Shortening the project duration by reducing the time of one or more critical activities | ||
| Doing technical analysis of the finished work for review |