Project: Create a database application for the shipping department.
Tasks:
First, schedule meeting with shipping team members (1 day)
After the meeting is scheduled, conduct meeting (1 day)
After meeting is conducted, start two tasks at once: organize information (1 day)
and create a plan (1 day)
After information is organized and plan is created, create database (1 day)
After database is created, meet with shipping team members to test database (1 day)
After database is tested, make any necessary modifications (1 day)
After modifications, deploy database (1 day)
After deployment of database, train users (1 day)Instructions: Create a work breakdown structure that includes a Gantt chart using the following format in Figure 2-1 below. Section 3.2 in the book
discusses how to create a WBS. Figure 3-9 provides an example of a completed WBS and a completed Gantt chart.
Figure 2-1
Another important aspect of project management is risk management, which includes identifying risks that may negatively impact a project and creating a risk
management plan and a risk response plan. Consider some of the risks that may affect the successful completion of the database. List at least three of the risks, determine
the probability of the risk occurring (high, medium, or low) and the negative impact of the risk if it does occur (high, medium, low). Create a risk matrix using the format
below for listing the risk, the impact, and the probability. Note that the impact will be high, medium, or low, and the probability will be high, medium, or low. Note that
section 3.8 in the book discusses risk management.
Risk 1-impact -(high, medium, or low), probability -(high, medium, or low)
Risk 2- impact -(high, medium, or low), probability -(high, medium, or low)
Risk 3-imbact -(hiah. medium, or low), probabilitv -(hiah. medium. or low)
 Project: Create a database application for the shipping department. Tasks: First,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!