Question: Project data is presented in Table 1 for a project that is currently at day 30. Activities have been started at the earliest possible start

Project data is presented in Table 1 for a project that is currently at day 30. Activities have been started at the earliest possible start date and costs are committed at activity start. Activities F and G are underway. Table 1. Project Data. Activity Predecessors Duration [days] Budget Cost [SK] Duration [days] Actual Actual % Cost [$K] Complete A None 8 400 9 425 100% B None 12 36 12 38 100% C None 8 96 5 92 100% D A 7 280 7 280 100% E A, B 15 105 15 110 100% F C, E 12 96 112 50% G D, E 4 100 85 75% H F 3 30 0 0% Instructions: 1. Draw the AOA network for this project in Microsoft PowerPoint (not in Microsoft Project). 2. Calculate the critical ratio. Show your work 3. Based on the critical ratio determine if the project is in control

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!