Question: Project _ _ _ _ _ _ _ _ depends on prompt and candid feedback from the project team, while _ _ _ _ _

Project ________ depends on prompt and candid feedback from the project team, while ________ depends on systems and decision rules for managing variances between the projects scope, cost, and schedule.
Question 4 options:
A)
Critical path; scope creep
B)
Monitoring; control
C)
Management; monitoring
D)
Timeline; baseline