Question: project described by: table [ [ Activity , table [ [ Immediate ] , [ Predecessor ] ] , table [ [

project described by:
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Time],[(days)]]],[A,-,6],[B,A,2],[C,-,8],[D,B, C,5],[E,D,7]]
has a critical path of length of
15 days
22 days
17 days
18 days
20 days
 project described by: \table[[Activity,\table[[Immediate],[Predecessor]],\table[[Time],[(days)]]],[A,-,6],[B,A,2],[C,-,8],[D,B, C,5],[E,D,7]] has a critical path of length