Question: Project Description The new computer - controlled conveyor belt is an exciting project that moves and positions items on the conveyor belt within < 1

Project Description
The new computer-controlled conveyor belt is an exciting project that moves and positions items on the conveyor belt within <1 millimeter. The project will produce a new system for future installations, and for replacement of those in the field, at a low cost. The computer- controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems installed in factories. The new system is also easier to update with future technologies.
The Project Priority Matrix for the Conveyor Belt Project (CBP) is:
Time Scope Cost
Constrain X
Enhance X
Accept X
Table A2.9 has been developed for you to use in completing the project exercises.
TABLE A2.9
Conveyor Belt Project; WBS
Conveyor Belt Project
Hardware
Hardware specifications Hardware design Hardware documentation Prototypes Order circuit boards Assemble preproduction models
Operating system
Kernel specifications Drivers Disk drivers Serial I/O drivers Memory management Operating system documentation Network interface
Utilities
Utilities specifications Routine utilities Complex utilities Utilities documentation Shell
System integration
Architectural decisions
Integration first phase System hard/software test Project documentation Integration acceptance testing
Assignment
Develop the WBS outline using the software available to you.
Question
Does this information (WBS) allow you to define any milestones of the project? Why or why not? What are they?
Remember: Save your file for future exercises!
Part 2
Use your file from Part 1 and the information provided below to complete this exercise. (See Table A2.10.)
Each work package will represent an activity. The project begins January 4,2010.
The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off.
The project teams work eight-hour days, Monday through Friday.
Warning: Experience has taught students to frequently make separate backup files for each exercise. The software is never as friendly as users expect!
Construct a network schedule for the conveyor belt project and prepare a memo that addresses the following questions:
When is the project estimated to be completed? How long will the project take? What is the critical path(s) for the project?
Which activity has the greatest amount of slack? How sensitive is this network?
Identify two sensible milestones and explain your choices.
Compare the advantages/disadvantages of displaying the schedule as a network versus a Gantt chart.
TABLE A2.10 Conveyor Belt Project; Schedule
Description
Architectural decisions
Harduare specifications
Kernel specifications
Uiities specifications.
Hardware design
Disk divers
Memory management
Operating system documentation
Route utes
Complex uiities
Utites documentation
Hardvare documentation
Intagraion fist phase
Prototypes
Serial U0 divers
System hardisoftuare test
Order circu boards.
Netvork interface
Shall
Project documentation
Assemble preproduction models
Integrated acceptance testing
Resource
Design
Development, design
Design
Development, design
Design, development
Assembly, development
Development
Design, documentation
Development
Development
Documentation, design
Documentation, design
Assembly, development
Assembly, development
Development
Assembly
Purchasing
Development
Development
Documentation, development
Assembly, development
Assembly, development
Duration (days)
5
0
2
15
7
100
=
El
El
Preceding Activity
1
17F-5,1ag 50 days
18,19,20,21
Note: F-S refers to a Finish-to-Start lag.
Include the following printouts:
A Gantt chart.
A network diagram highlighting the critical path.
A schedule table reporting ES, LS, EF, LF, and slack for each activity.
Hint: The project should be completed in 530 days
ChatGPT
First, let's develop the Work Breakdown Structure (WBS) outline based on the provided information:
mathematica
Copy code
Conveyor Belt Project WBS
1. Project Management
1.1 Project Planning
1.2 Project Execution
1.3 Project Monitoring and Control
1.4 Project Closure
2. Hardware
2.1 Hardware Specifications
2.2 Hardware Design
2.3 Hardware Documentation
2.4 Prototypes
2.5 Order Circuit Boards
2.6 Assemble Preproduction Models
3. Operating System
3.1 Kernel Specifications
3.2 Drivers
3.2.1 Disk Drivers
3.2.2 Serial I/O Drivers
3.3 Memory Management
3.4 Operating System Documentation
3.5 Network Interface
4. Utilities
4.1 Utilities Specifications
4.2 Routine Utilities
4.3 Complex Utilities
4.4 Utilities Documentation

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!