Question: project has the following activities, with specified precedents and expected durations (in hours). What is the expected project duration? Activity Precedent Duration A - 6.0
project has the following activities, with specified precedents and expected durations (in hours). What is the expected project duration?
| Activity | Precedent | Duration |
| A | - | 6.0 |
| B | - | 7.2 |
| C | A | 4.9 |
| D | B, C | 6.0 |
| E | B, C | 4.5 |
| F | D | 7.7 |
| G | E, F | 4.0 |