Question: Project Information for Homework #1 ID Activity Predecessor Time (Days) A Order Review None 2 B Order Standard Parts 15 Produce Standard Parts A 10



Project Information for Homework #1 ID Activity Predecessor Time (Days) A Order Review None 2 B Order Standard Parts 15 Produce Standard Parts A 10 D Design Custom Parts A 13 E Manufacturing Custom Hardware CD 15 10 F BE Assemble F Test un G The Early Start (ES) time for Activity F Assemble is days. The Early Finish (EF) time for Activity B Order Standard Part is days. Question 4 0 / 10 pts The Late Start (LS) time for Activity B Order Standard Parts is days