Question: Project information has been distributed according to the communications plan. Some project deliverables have been changed. Those changes were made according to the change control

Project information has been distributed according to the communications plan. Some project deliverables have been changed. Those changes were made according to the change control process. One stakeholder expressed surprise to the project manager upon being informed of a previously published change to a project deliverable. All stakeholders received the communication containing notification of the change. What should the project manager do? Select one:

a. Review the communications plan and make revisions, if necessary

b. Address the situation in the next steering committee meeting so others do not miss published changes

c. Determine why the stakeholder did not receive the information and let him know when it was published

d. Ask the functional manager why the stakeholder did not understand his responsibility

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!