Project L requires an initial outlay at t = 0 of $60,000, its expected cash inflows are
Fantastic news! We've Found the answer you've been seeking!
Question:
Project L requires an initial outlay at t = 0 of $60,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 9%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.