Question: Project Loon software by Google X . Using the complexity weighing scheme and the function point complexity weight table shown below, estimate the total function
Project Loon software by Google X. Using the complexity weighing scheme and the function point complexity weight table shown below, estimate the total function point count. Assume five function points equal one person a month and 8 people can work on the project.
a. What is the estimated project duration?
b. If each person charges $1000 per month, what is the total project cost?
c. If 14 people are available for the project, what is the estimated project duration?
| Inputs | 10 | Rated Complexity low (2) |
| Outputs | 20 | Rated Complexity average (6) |
| Inquiries | 10 | Rated Complexity average (4) |
| Files | 30 | Rated Complexity high (12) |
| Interfaces | 50 | Rated Complexity high (10) |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts