Question: Project Management. A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:

Project Management. A company must perform a

Project Management. A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: Activity Immediate Predecessor Time in Days A None 3 B 3 A 3 D B 4 E 2 F D and E 1 G F 2 Using CPM, which activities make up the critical path? O None of these O A, C, E, F, G O A, C, B, F, E O A, B, D, F, G