Question: project management a. Find the Critical Path, Project Time. b. Find the slack times for each activity c. Create a resource loading on below given

project management a. Find the Critical Path,

project management

a. Find the Critical Path, Project Time.

b. Find the slack times for each activity

c. Create a resource loading on below given table and if needed perform resource leveling on the project composed of the activities in this table. Activities listed in the table are measured in the number of 8-hours by day. The maximum amount of time used per day is 16 hours.

2. Based on the table given below, A B E F Activity Time 6 D 5 G 2 2 3 3 2 Predecessor A B A D E,F a. Find the Critical Path, Project Time. b. Find the slack times for each activity c. Create a resource loading on below given table and if needed perform resource leveling on the project composed of the activities in this table. Activities listed in the table are measured in the number of 8-hours by day. The maximum amount of time used per day is 16 hours. Act 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 A | D JE F G H Tot

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!