Question: Project Management Answer the following questions using your textbook and the PowerPoint slides on EVA: 1. How is ROM estimate different from definitive cost estimate?
Answer the following questions using your textbook and the PowerPoint slides on EVA: 1. How is ROM estimate different from definitive cost estimate? Explain with examples of both. - 4 points 2. What do you need to do before beginning a cost estimate? - 3 points 3. Assume you are managing a project that has a schedule goal of 12 months. The total cost (BAC) of the project is $200,000.00. Six months have passed and $145,000.00 is spent. A closer review of the project reveals that 35% of the work has been completed so far. Calculate the following: - At points - PV - EV - SV . CV - SPI - CPI - EAC 4. Based on the CPI, how is the project doing? -2 points