Question: Project Management Assignment 2 _ 2 : Project Scheduling Questions Why does the scheduling function depend on the planning function? Which one must be done

Project Management
Assignment 2_2: Project Scheduling
Questions
Why does the scheduling function depend on the planning function? Which one must be done
first? Why?
Describe what an activity estimated duration is. How is it determined?
Why might a contractor prefer to state a project completion time in terms of number of days after
the project starts rather than a specific date? Give some examples of instances when this would be
appropriate.
Describe the different types of project slack and how each is calculated. Why is it important to
determine the critical path of a project? What happens if activities on this path are delayed? What
happens if activities on this path are accelerated?
Why should a project have a regular reporting period? Should all projects have the same reporting
period?
Describe how you would apply the four steps of schedule control to a project. If the project needs
to be accelerated, what kinds of activities would be the primary focus? Why?
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and
identify the critical path for the project. Can the project be completed in 40 weeks? Assume that
activity A actually finished at 3 weeks, activity B actually finished at 12 weeks, and activity C
actually finished at 13 weeks. Recalculate the expected project completion time. Which activities
would you focus on to get the project back on schedule?
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and
identify the critical path for the project. Can the project be completed in 30 weeks? Assume that
"Systems Analysis" actually finished at 8 weeks. "Design Input & Output" actually finished at 15
weeks, and "Design Database" actually fimished at 19 weeks. Recalculate the expected project
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and
identify the critical path for the project. Can the project be completed in 40 weeks? Assume that
activity A actually finished at 3 weeks, activity B actually finished at 12 weeks, and activity C
actually finished at 13 weeks. Recalculate the expected project completion time. Which activities
would you focus on to get the project back on schedule?
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and
identify the critical path for the project. Can the project be completed in 30 weeks? Assume that
"Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15
weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project
completion time. Which activities would you focus on to get the project back on schedule?
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and
identify the critical path for the project. Can the project be completed in 40 weeks? Assume that
activity A actually finished at 3 weeks, activity B actually finished at 12 weeks, and activity C
actually finished at 13 weeks. Recalculate the expected project completion time. Which activities
would you focus on to get the project back on schedule?
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and
identify the critical path for the project. Can the project be completed in 30 weeks? Assume that
"Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15
weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project
completion time. Which activities would you focus on to get the project back on schedule?
 Project Management Assignment 2_2: Project Scheduling Questions Why does the scheduling

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!