Question: project management: Case Study task 1: CASE STUDY: Small Project Cost Estimating Leah graduate d in July 2012 with a degree in Business majoring in
Small Project Cost Estimating
Leah graduated in July 2012 with a degree in Business majoring in Project Management. She accepted a job as a project coordinator for Housing New Zealand in the Building Maintenance department. She worked on fixed cost estimates for housing projects, where the work was uncomplicated to estimate, and she worked with experienced building teams and a supportive management team which allowed her to generate accurate quotes most of the time, a few quotes were +/-10% on the original quote however this was an acceptable margin for maintenance quotes such as these.
Leah had been promoted to a new position in Housing New Zealand to the project office. Her responsibility now was to coordinate estimates for all major projects for the company.
The project was to build low cost housing units on land owned by Housing New Zealand. The cost of the houses was estimated to be $400,000. Leah attended a Kick-Off meeting to approve the Charter of the project, where the management team approved the budget overall budget of the project at $500,000 with a budget of the product at $400,000. This type of project had never been planned and executed before, but the management team were confident in the estimates from information from previous projects.
Couple of senior contractors were worried about materials required to build the low cost housing to Council Standards with the $400,000 budget. But given the excitement of the moment, everyone agreed the project was worth doing and was possible to execute. This project was to have the highest project priority in the company.
Estimates were due in two weeks.
Leah started off by compiling estimates for the project. The corresponding cost estimates had seemed to be in error. The cost estimate was $80,000 over the management estimate; this represents about 20 percent over run.
The time estimate from the developed project network was only four months over managements time estimate. Another meeting had been scheduled with the significant stakeholders for checking the estimates and to brainstorm for alternatives solutions; the cost and time estimates appeared to be reasonable. Some of the suggestions for the brainstorming session are listed below.
Very little in the way of concrete savings was identified, even though there was consensus that time could be compressed to the proposed dates, but at additional costs.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
