Question: Project Management - Chapter 5: Estimating Project Times and Cost . Q4. Answer the below questions. a) Briefly explain the Apportion method and discuss when
Project Management - Chapter 5: Estimating Project Times and Cost .

Q4. Answer the below questions. a) Briefly explain the Apportion method and discuss when it is applied. In b) Given the below WBS of the "e-Commerce Website for Eureka" project, calculate the cost for each of the project deliverables. ( e-Commerce Website for Eureka Defining and Planning Closing Executing Status reports Changes Forecasts Kick-off meeting Schedules Risks Staffing Train customer Transfer documents . Below are provided the cost details: Total Cost: 100 000 KWD Defining and Planning (30%) Kick-off meeting (2%) Schedules (4%) Risks (4%) Staffing (20%) Executing (50%) Status reports (5%) Changes (40%) Forecasts (5%) Closing (20%) Train customer (10%) Transfer documents (10%)