Question: project management E. Using the following values, calculate ETC (estimate to complete), assuming that the work is progressing as planned: estimate at completion =55,000, actual

project management
project management E. Using the following values, calculate ETC (estimate to complete),

E. Using the following values, calculate ETC (estimate to complete), assuming that the work is progressing as planned: estimate at completion =55,000, actual cost=45,000, earned value =40,000, planned value =42,000 15,000 10,000 13,000 12,000