Question: Project Management HW Name :------------------------------------------------- ID:------------------- Question 1 Use the following information in the table to answer question. ( 6 points) Year Project A Project

Project Management

HW

Name:-------------------------------------------------ID:-------------------

Question 1 Use the following information in the table to answer question. (6 points)

Year Project A Project B

1150000 50000

2200000 150000

3250000 200000

4150000 300000

5100000 200000

Two projects A and B are available each costing $ 500000. In comparing the profitability of projects a discounted rate of 10% is to be used. Indicate which of the project is would be more profitable investment using

1. Discounted Payback period method
2. NPV method
3. Profitability Index
4. Undiscounted Payback period method

Question 2: The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2017, and be completed in time for the start of the 2020 season. A penalty clause of $100,000 per day of delay beyond May 20, 2020, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes.

Given the information provided in the following table, construct a network schedule for the stadium project and answer the following questions: (8.5 points)

1. Will the project be able to be completed by the May 20 deadline? How long will

it take?

2. What is the critical path for the project?

3. Based on the schedule would you recommend that G&E pursue this contact?

Why? Include a one-page Gantt chart for the stadium schedule.

ID

Activity

Duration (days)

Predecessor(s)

1

Baseball Stadium

2

Clear stadium site

70

-

3

Demolish building

30

2

4

Set up construction site

70

3

5

Drive support piling

120

2

6

Pour lower concrete bowl

120

5

7

Pour main concourse

120

3,6

8

Install playing field

90

3,6

9

Construct upper steel bowl

120

3,6

10

Install seats

140

7,9

11

Build luxury boxes

90

7,9

12

Install jumbo Tron

30

7,9

13

Stadium infrastructure

120

7,9

14

Construct steel canopy

75

10

15

Light installation

30

14

16

Build roof supports

90

6

17

Construct roof

180

16

18

Install roof tracks

90

16

19

Install roof

90

17,18

20

Inspection

20

8,11,13,15,19

Question 3: Using Apportion method, what are the estimated costs for the following deliverables if the total project cost $850 000. (5.5points)

Router systems project

100%

Definition (A activity)

15%

Design (B activity)

35%

Implementation (C activity)

60%

( sub activities /A)

Objectives

10%

Requirements

5%

( sub activities /B)

Inputs

15%

Outputs

8%

Files

7%

Programming

5%

( sub activities /C)

In house testing

32%

Customer testing

28%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!