Question: Project Management --I need help with this questions........ A project manager learns that tasks assigned to the team weeks ago are not complete. The manager
Project Management --I need help with this questions........
- A project manager learns that tasks assigned to the team weeks ago are not complete. The manager did not meet with the team members to discuss progress and did not provide guidance on the task.
Which skill is this project manager is lacking?
Procurement
Business Management
Leadership
Strategic Management
- Which process defines stakeholders expectations
Collect requirements
Develop Project Charter
Sequence Activities
Perform Change control
- Which input to the Direct and Manage Project Work process provides information on threats and opportunities that may affect project execution?
Schedule Forecast
Risk Register
Quality report
Issue log
- Which activity should be performed as part of the Direct and Manage Project work process?
Update project management Information systems
Create a risk report
Create a project change management plan
Create a lesson learned register
- An organization is ready to baseline a project management plan. A team member discovers a critical missing requirement and asks the team to modify the project plan
What should the project manager do next?
Make the request change
Consult the change control board
Mark this as scope creep
Implement a formal change request
- Which technique is used to build a project charter?
Expert Judgment
- A project manager is monitoring and controlling a project. The project manager completes a financial analysis for the project and needs to alert stakeholders.
What should the manager create?
Change requests
Management plan updates
Document updates
Work performance report
Step by Step Solution
There are 3 Steps involved in it