Question: PROJECT MANAGEMENT If ES = 5, LS = 8, and EF = 9, then LF =: O A. B. 17 C. 12 D. 9 An
PROJECT MANAGEMENT




If ES = 5, LS = 8, and EF = 9, then LF =: O A. B. 17 C. 12 D. 9 An effective project manager should be able to: A write an exciting recruiting ad B. criticize team members without hurting their feelings C. design a career ladder D. manage conflict Previous page Primary responsibility for quality in a project rests with the: A. executive sponsor B. project manager C. quality department manager D. senior project engineer Scope creep is most likely to result from: A. too many levels in the WBS B. unskilled team members C. highly detailed specifications O D. unclear product characteristics