Question: Project Management Part E The following table provides the information necessary to construct a project network and project crash data. Maximum Duration Reduction Activity Predecessor
The following table provides the information necessary to construct a project network and project crash data. 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of the whole project. 4. What activities should be crashed by how many weeks in order to reduce the duration of the whole project by 5 weeks