Question: PROJECT MANAGEMENT PLEASE ANSWER WITH A PICTURE, I need a diagram please Construct an Activity-on-Arrow (AOA) network and an Activity-on-Node (AON) network for a project
PROJECT MANAGEMENT
PLEASE ANSWER WITH A PICTURE, I need a diagram please
Construct an Activity-on-Arrow (AOA) network and an Activity-on-Node (AON) network for a project comprised of activities A to P that satisfies the following precedence relationships.
- A, B, and C, the first activities of the project, can be executed concurrently.
- D, E, and F follow A.
- I and G follow both B and D.
- H follows both C and G.
- K and L follow I.
- J succeeds both E and H.
- M and N succeed F, but cannot start until both E and H are completed.
- O succeeds M and I.
- P succeeds J, L, and O.
- K, N, and P are the terminal activities of the project.