Question: Project Management Practical 2 Fine Wines: Old wine in a new database The company Fine Wines PLC is introducing a new database at its world
Project Management
Practical 2
Fine Wines: Old wine in a new database
The company Fine Wines PLC is introducing a new database at its world HQ offices. The Fast Software Company has assigned a team of three programmer/analysts to the project. The following tasks have been established. Input data into ProjectLibre.
| Task Details | Duration | Immediate Predecessors | Resources |
| 1. define requirements | 2w |
| JOHN, SUE |
| 2. design database | 2w | 1 | JOHN, SUE |
| 3. set up data template | 1w | 2SS+1w | JOHN |
| 4. select software | 4w | 2 | SUE |
| 5. select hardware | 3w | 4 | ALAN |
| 6. train users in data entry | 2w | 3 | JOHN, ALAN |
| 7. test users | 4w | 6FS+2w | JOHN, SUE |
| 8. program database | 2w | 7,10 | ALAN |
| 9. procedures manual | 2w | 7 | JOHN |
| 10. install hardware, inc. network | 3w | 5FS+2w | SUE |
| 11. install help software | 1w | 9,10 | ALAN |
| 12. final training program | 1.5w | 8,11 | JOHN, SUE |
| 13. test final system | 1w | 12 | SUE, ALAN |
| 14. final closeout | 4w | 12,13 | ALAN |
Resource Costing
John, Sue $200 / hour
Alan $400 / hour
- Calculate the overall duration and the cost required to complete the Project.
- How much does John, Sue and Alan cost the Project?