Question: Project Management Practical 2 Fine Wines: Old wine in a new database The company Fine Wines PLC is introducing a new database at its world

Project Management

Practical 2

Fine Wines: Old wine in a new database

The company Fine Wines PLC is introducing a new database at its world HQ offices. The Fast Software Company has assigned a team of three programmer/analysts to the project. The following tasks have been established. Input data into ProjectLibre.

Task Details

Duration

Immediate Predecessors

Resources

1. define requirements

2w

JOHN, SUE

2. design database

2w

1

JOHN, SUE

3. set up data template

1w

2SS+1w

JOHN

4. select software

4w

2

SUE

5. select hardware

3w

4

ALAN

6. train users in data entry

2w

3

JOHN, ALAN

7. test users

4w

6FS+2w

JOHN, SUE

8. program database

2w

7,10

ALAN

9. procedures manual

2w

7

JOHN

10. install hardware, inc. network

3w

5FS+2w

SUE

11. install help software

1w

9,10

ALAN

12. final training program

1.5w

8,11

JOHN, SUE

13. test final system

1w

12

SUE, ALAN

14. final closeout

4w

12,13

ALAN

Resource Costing

John, Sue $200 / hour

Alan $400 / hour

  1. Calculate the overall duration and the cost required to complete the Project.

  1. How much does John, Sue and Alan cost the Project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!