Question: Project Management Practice Problem Bragg's Bakery is building a new automated bakery downtown Sandusky. Here are the activities that need to be completed to get

Project Management Practice Problem Bragg's

Project Management Practice Problem Bragg's Bakery is building a new automated bakery downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed. ACTIVITY PREDECESSOR NORMAL TIME (WEEK) 9 B D E F A A B,C D,E 8 15 5 10 2 CRASH TIME (WEEK) 6 5 10 3 6 1 EXPEDITING COST/WEEK 3000 3500 4000 2000 2500 5000 Hint: I have directly provided the crashing cost per unit time. What is the normal project length