Question: PROJECT MANAGEMENT QUESTION BASED ON THIS DIAGRAM: activity predecessor duration early start late start early finish late finish a -- 12 b a 20 c

PROJECT MANAGEMENT QUESTION BASED ON THIS DIAGRAM:

activity predecessor duration early start late start early finish late finish
a -- 12
b a 20
c a
d b,e 42
e c 28 42
f e 42 50
g d 53 53
h g 70
i g 72
j f 4
k h,I,j 81 91

how would I use a forward-pass and backward-pass to finish this task grid to find the critical path of the event?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!