Question: PROJECT MANAGEMENT QUESTION BASED ON THIS DIAGRAM: activity predecessor duration early start late start early finish late finish a -- 12 b a 20 c
PROJECT MANAGEMENT QUESTION BASED ON THIS DIAGRAM:
| activity | predecessor | duration | early start | late start | early finish | late finish |
| a | -- | 12 | ||||
| b | a | 20 | ||||
| c | a | |||||
| d | b,e | 42 | ||||
| e | c | 28 | 42 | |||
| f | e | 42 | 50 | |||
| g | d | 53 | 53 | |||
| h | g | 70 | ||||
| i | g | 72 | ||||
| j | f | 4 | ||||
| k | h,I,j | 81 | 91 |
how would I use a forward-pass and backward-pass to finish this task grid to find the critical path of the event?