Question: Project Management Question, Please answer all questions The function of project managers is to (circle all that apply): mediate between the higher (institutional) levels and
Project Management Question, Please answer all questions
- The function of project managers is to (circle all that apply):
- mediate between the higher (institutional) levels and lower (technical) levels in the project
- integrate and coordinate the tasks of the technical level in the project
- conceive the long-term goals of the organization
- provide detailed guidance and control over all work at the technical level
- A complete proposal should not include:
- description of the project organization
- project purpose, objectives, and work approach
- time and cost estimates
- a brief resume of key personnel
- all of the above should be included
- A complete RFP should include (circle all that apply):
- a statement describing the contractor who will perform the work
- a statement of the problem or work to be performed
- information about the state of the economy
- information about the expected proposal format and content
- information about the selection timetable, criteria, and contract type
- In defining user needs, which of the following are true (circle all that apply):
- the contractor defines the need first, then checks it with the customer.
- the user always knows what his needs are.
- there might be more than one user.
- the contractor should redefine the need in terms of the area in which he (the contractor) knows the most or has the greatest expertise
- some of the needs might change and have to be redefined later
- So that the user can remain impartial, during the feasibility study the contractor should sever or minimize communication with the user.
- True
- False
- The purpose of contract negotiation is to (circle all that do not apply):
- clarify technical terms of the contract
- reach agreement on time, cost, and performance requirements
- convince the user that the project has been completed
- reach a contract agreement to the best advantage of the parties involved
- The requirements breakdown structure (circle all that apply):
- is a comprehensive list of requirements
- groups requirements into categories
- is prepared by the customer or users for contractors
- The project charter (circle all that apply)
- Is typically applied in internal projects.
- Describes the project to stakeholders and establishes the project managers authority to gather resources.
- Often contains sections similar to the project plan (e.g., objectives, scope, stakeholders, estimated budget, schedule, risk, assumptions and constraints, resources, etc.)
- Is a section with the RFP or project proposal.
- Each functional requirement (circle all that apply)
- must be assessed for the best way to satisfy it
- can be satisfied using either off-the-shelf (OTS) or brand-new designs or product
- might have to be revised if good solutions are not available
- Which one he following is true:
- the WBS is the basis for project schedules, budgets, and controls.
- work packages are the basis for project schedules, budgets, and control.
- project schedules are the basis for work definition.
- A well-defined task includes (circle all that apply):
- resources requirements
- resumes of workers
- times and cost estimates
- definition of the deliverables, outputs, or results
- persons or groups responsible for the task
- The responsibility matrix shows (circle all that apply):
- tasks and the people responsible for them
- for certain people, the tasks for which they are responsible
- the nature of responsibilities in a project
- how costs change with the project responsibilities
- The scope statement specifies the main areas of work to be performed and the intended deliverables or end items.
- True
- False
- Functional flow block diagrams (FFBSs) show (circle all that apply):
- the breakdown of functions, requirements, or elements into smaller functions, requirements, or elements
- the clustering of functions into physical modules or system components
- the interfaces among functions, requirements, or element
- A system specification is a translation of user requirements into technical terms.
- True
- False
- Since system specifications are usually too detailed for users to understand,
generally they are not reviewed with the user
- True
- False
- The critical path(circle all that apply):
- is shortest path through a project network
- does not change during project execution.
- Always has zero slack
- Has the smallest slack in the project.
- all of the above.
- In a start-to-start relationship, a 2-day lag implies that
- the successor should not start until two days after the predecessor has been completed.
- the successor should not start until two days after the predecessor has started.
- the successor can start two days before the predecessor has started
- the two activities can start on the same date.
- Resource leveling
- makes use of float (slack) to move activities to time slots other than the as early as possible dates
- makes the workload on resources more evenly distributed.
- can potentially turn non-critical activities into critical ones.
- all of the above.
- (a) and (b) above.
- Functional requirements (circle all that apply):
- assist stakeholders in defining user requirements
- include performance requirements and verification requirements
- are the result of requirements analysis
- Which statement is correct: In the CPM, as the duration of a project is decreased, usually:
- so are both its direct and indirect costs
- direct costs increase, but indirect costs decrease
- both direct and indirect costs increase
- direct costs decrease, indirect costs increase
- When there are multiple critical paths and the project duration must be reduced, it is necessary to make reductions:
- on whichever critical path affords the smallest cost increase
- on whichever non-critical path affords the smallest cost increase
- that will shorten all of the critical paths
- that will shorten all of the non-critical path
- To reduce the duration of a project using CPM, it is necessary to make a reduction
on the activity with:
- the largest cost slope on the critical path (CP)
- the smallest cost slope on the CP
- the largest cost slope not on the CP
- the smallest cost slope not on the CP
- Managing a system to achieve effective, coordinated functioning of its elements working toward system objectives is called (circle one);
- systems definition
- systems integration
- systems development
- systems forecasting
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
