Question: Project Management question. Please answer questions: a,b &c in written detail. Thanks for your help. c) Show that 80% is for the Confidence Interval for

Project Management question.
Please answer questions: a,b &c in written detail.
Thanks for your help.
c) Show that 80% is for the Confidence Interval for the project.
Project Management question. Please answer questions: a,b &c in written detail. Thanks
for your help. c) Show that 80% is for the Confidence Interval

Consider the following project. Use activity times as the most likely time for determining the critical path. Use the optimistic and pessimistic times (together with activity times) to determine expected completion time limits a. Draw PERT Chart with earliest and latest start and finish times/activity. Fill in the slack time in the table for each activity. Show the slack time for each path for all paths and show Critical Path (CPM) and CPM time. b. What is the expected time for 68,95 and 99 percent Confidence Interval (CI) for the project? \begin{tabular}{|c|c|c|c|c|c|c|c|} \hline ID 3 & Preceeding & Start & End & Activity & Staff & Optimistic & Pessimistic \\ \hline Activity & Activity & Node & Node & Time & Required & Time & Time \\ \hline A & & S & 1 & 3 & 4 & 3 & 4 \\ \hline B & & S & 2 & 2 & 2 & 3 & 5 \\ \hline C & & S & 3 & 4 & 6 & 1 & 3 \\ \hline D & A, B & 1 & 4 & 5 & 4 & 3 & 5 \\ \hline E & B & 2 & 5 & 3 & 2 & 3 & 6 \\ \hline F & E & 5 & End & 2 & 4 & 3 & 5 \\ \hline G & C, E & 3 & End & 8 & 7 & 3 & 7 \\ \hline H & D & 4 & End & 6 & 4 & 3 & 7 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!