Question: Project Management School Library Renovation I need help creating a Risk Management Plan Use the information provided to create a Risk Management Plan Schedule :

Project Management

School Library Renovation

I need help creating a Risk Management Plan

Use the information provided to create a Risk Management Plan

Schedule: Stakeholder interviews can begin as early as Monday, 5/3/2021. No work will be conducted on weekend days nor holidays. Also, remember that no physical work (Activity 2.2 Demolition) can be conducted on campus until Tuesday, 6/1/2021. The schools holiday schedule includes Friday, 7/2/2021 and Monday, 7/5/2021 as non-working days due to the July 4th Holiday.

Work package

Duration (days)

Task Precedence

1.1

Stakeholder interviews

3

None

1.2

Architect selected

1

1.1

1.3

Concept plans created

3

1.2

1.4

Concept plan meeting

1

1.3

1.5

Design approved

1

1.4

1.6

Furniture ordered

1

1.5

1.7

General contractor selected

1

1.2 & 1.5

2.1

Building permit received

2

1.5

2.2

Demolition

4

1.7 & 2.1

2.3

Walls constructed

3

2.2

2.4

M/E systems installed

5

2.3

2.5

Painting/carpet completed

2

2.4

2.6

Final inspection

1

2.5

3.1

Furniture delivered

1

1.6 & 2.6

3.2

Furniture installed

2

3.1

3.3

Stakeholder walkthrough

1

3.2

3.4

Project closeout

1

3.3

.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!