Question: Project Management School Library Renovation I need help creating a Risk Management Plan Use the information provided to create a Risk Management Plan Schedule :
Project Management
School Library Renovation
I need help creating a Risk Management Plan
Use the information provided to create a Risk Management Plan
Schedule: Stakeholder interviews can begin as early as Monday, 5/3/2021. No work will be conducted on weekend days nor holidays. Also, remember that no physical work (Activity 2.2 Demolition) can be conducted on campus until Tuesday, 6/1/2021. The schools holiday schedule includes Friday, 7/2/2021 and Monday, 7/5/2021 as non-working days due to the July 4th Holiday.
| Work package | Duration (days) | Task Precedence | |
| 1.1 | Stakeholder interviews | 3 | None |
| 1.2 | Architect selected | 1 | 1.1 |
| 1.3 | Concept plans created | 3 | 1.2 |
| 1.4 | Concept plan meeting | 1 | 1.3 |
| 1.5 | Design approved | 1 | 1.4 |
| 1.6 | Furniture ordered | 1 | 1.5 |
| 1.7 | General contractor selected | 1 | 1.2 & 1.5 |
| 2.1 | Building permit received | 2 | 1.5 |
| 2.2 | Demolition | 4 | 1.7 & 2.1 |
| 2.3 | Walls constructed | 3 | 2.2 |
| 2.4 | M/E systems installed | 5 | 2.3 |
| 2.5 | Painting/carpet completed | 2 | 2.4 |
| 2.6 | Final inspection | 1 | 2.5 |
| 3.1 | Furniture delivered | 1 | 1.6 & 2.6 |
| 3.2 | Furniture installed | 2 | 3.1 |
| 3.3 | Stakeholder walkthrough | 1 | 3.2 |
| 3.4 | Project closeout | 1 | 3.3 |
.