Question: Project management software systems can be used to map out a project in different ways according to its complexity. Which of the following statements lists
Project management software systems can be used to map out a project in different ways according to its complexity. Which of the following statements lists software results according to lowtohigh project complexity?
Multiple Choice
Gantt chart, flow chart, PERT chart
flow chart, PERT chart, Gantt chart
flow chart, Gantt chart, PERT chart
PERT chart, Gantt chart, flow chart