Question: Project Management The following data pertains to a certain project: Immediate Predecessor. Crash Time (weeks) 6 Activity A B D E F Resources Worker 01

Project Management

Project Management The following data pertains to

The following data pertains to a certain project: Immediate Predecessor. Crash Time (weeks) 6 Activity A B D E F Resources Worker 01 Worker 02 Worker 03 Worker 02 Worker 04 Worker 05 Normal Time (weeks) 10 8 10 7 10 3 Normal Cost 30 120 100 40 50 60 Crash Cost 70 150 160 50 75 95 B A D CE 6 8 1 (a) Develop the project network of the problem. (05) (b) Find the Critical chain using step by step procedure and time duration of the project given in the Question 01. (20)