Question: Project Management You are a project manager. Based on the activities shown in Table 2, prepare a work plan schedule. Draw a Network diagram for

Project Management You are a project manager. Based on the activities shown in Table 2, prepare a work plan schedule.

  1. Draw a Network diagram for this project.

[4 marks]

  1. By completing Table 3, indicate the critical path and the project duration.

[16 marks]

Table 2

ACTIVITY

IPA*

DURATION

A

-

2

B

A

5

C

A

6

D

A

4

E

B, C

3

F

C, D

8

G

E

10

H

F

2

I

G, H

5

*Immediately Preceding Activities

Table 3

ID

Duration (weeks)

ES

EF

LS

LF

TF

FF

A

2

B

5

C

6

D

4

E

3

F

8

G

10

H

2

I

5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!