Question: Project Management You are a project manager. Based on the activities shown in Table 2, prepare a work plan schedule. Draw a Network diagram for
Project Management You are a project manager. Based on the activities shown in Table 2, prepare a work plan schedule.
- Draw a Network diagram for this project.
[4 marks]
- By completing Table 3, indicate the critical path and the project duration.
[16 marks]
Table 2
| ACTIVITY | IPA* | DURATION |
| A | - | 2 |
| B | A | 5 |
| C | A | 6 |
| D | A | 4 |
| E | B, C | 3 |
| F | C, D | 8 |
| G | E | 10 |
| H | F | 2 |
| I | G, H | 5 |
*Immediately Preceding Activities
Table 3
| ID | Duration (weeks) | ES | EF | LS | LF | TF | FF |
| A | 2 |
|
|
|
|
|
|
| B | 5 |
|
|
|
|
|
|
| C | 6 |
|
|
|
|
|
|
| D | 4 |
|
|
|
|
|
|
| E | 3 |
|
|
|
|
|
|
| F | 8 |
|
|
|
|
|
|
| G | 10 |
|
|
|
|
|
|
| H | 2 |
|
|
|
|
|
|
| I | 5 |
|
|
|
|
|
|