Question: project management You assume that cost efficiency will continue to be the same for the duration of the project. If EV=600,PV=500,AC=550,BAC=1,000, what is the EAC
project management
You assume that cost efficiency will continue to be the same for the duration of the project. If EV=600,PV=500,AC=550,BAC=1,000, what is the EAC (estimate at completion)? 450 500 833 917