Question: Project manager Daniel is currently executing a network upgrade project. The project has a budget of $4,000 and a duration of 4 years total. Daniel
Project manager Daniel is currently executing a network upgrade project. The project has a budget of $4,000 and a duration of 4 years total. Daniel just completed the 17th month of the project. The project team has completed 35% of the project work and has spent $1,500.
Summary:
Budget:. . . . . . . . . . . . .$4,000
Duration:. . . . . . . . . .. . 4 Years
Now. . . . . . . . . . . . . . . .17th month completed
Completed:. . . . . . . . . .35%
Total Spent:. . . . . . . .. .$1,500
Find the following values:
| BAC: | PV: | EV: | AC: |
| CV: | CPI: | SV: | SPI: |
| EAC: | ETC: | VAC: | TCPI: |