Question: Project manager Daniel is currently executing a network upgrade project. The project has a budget of $4,000 and a duration of 4 years total. Daniel

Project manager Daniel is currently executing a network upgrade project. The project has a budget of $4,000 and a duration of 4 years total. Daniel just completed the 17th month of the project. The project team has completed 35% of the project work and has spent $1,500.

Summary:

Budget:. . . . . . . . . . . . .$4,000

Duration:. . . . . . . . . .. . 4 Years

Now. . . . . . . . . . . . . . . .17th month completed

Completed:. . . . . . . . . .35%

Total Spent:. . . . . . . .. .$1,500

Find the following values:

BAC: PV: EV: AC:
CV: CPI: SV: SPI:
EAC: ETC: VAC: TCPI:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!