Question: project manager estimates a project will take 1 4 weeks at a cost of $ 6 0 , 0 0 0 . In signing the
project manager estimates a project will take weeks at a cost of $ In signing the contract documents, the customer imposes a penalty for late completion of $ per week for every week above weeks.The function manager estimates that themaximum possible crashing of the project duration is weeks at an additional cost of $ Assuming that the project manager is going to make the decision and that cost is the driving criteria for the project manager's organization, what is the expected project cost?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
