Question: project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule? Identify the longest activity path in the

project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule? Identify the longest activity path in the schedule with the shortest possible duration. Identify the crashed project schedule to find the shortest duration to complete the project. Identify the path through the schedule with leveled resources and the shortest duration. Identify the tasks with float duration, which do not impact the duration of the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!