Question: Project Manager has assigned 15 projects in his team to be completed in a 15-weeks. The engineers, of course, are moaning and groaning that the
Project Manager has assigned 15 projects in his team to be completed in a 15-weeks. The engineers, of course, are moaning and groaning that the load cannot possibly be completed in the time allotted Project Manager sympathetically suggests that the engieers work in groups and learn to organize their work efficiently. Knowing when a situation is hopeless, the engineers make a list of the tasks that have to be completed in preparing a project. These tasks are listed here, along with precedence requirements and estimated time in days. Assuming engineers will work five days a week on this, how many engineers should be assigned to each group, and what is the most efficient allocation of tasks? Can 15 projects be completed in 15 weeks? Explain your answer

UNA Element Description Precedence Time (days) Read Project expectations Gather required data Literature survey 3 Upload data 1 Run Computer D Analysis Project | Generate Report
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts