Question: Project Manager John Boy has a policy of only using experienced, dependable, and proven sellers instead of selecting sellers through open competition as a means

  1. Project Manager John Boy has a policy of only using experienced, dependable, and proven sellers instead of selecting sellers through open competition as a means to manage procurement risk. What risk management technique is John Boy using?

A. Risk Acceptance.

B. Risk Mitigation.

C. Risk Transfer

D. Risk Avoidance.