Question: Project Managment, Please help! Given the project data in the table below, (j) Draw a fully analyzed AON network diagram for the project, showing all
Project Managment, Please help!
Given the project data in the table below, (j) Draw a fully analyzed AON network diagram for the project, showing all ES, EF, LS and LF times. (ii) Determine the minimum cost of crashing the project duration by two weeks. Assume partial crashing is allowed. Do not use MSP! Task Immediate Predecessor Normal Duration (Weeks) Normal Cost ($ Crashed Duration (Weeks) Crashed Cost (S)
Step by Step Solution
There are 3 Steps involved in it