Question: Project network analysis Using 3 time estimates for each task the duration of project (critical path) was calculated to be 108 days with a variance
Project network analysis Using 3 time estimates for each task the duration of project (critical path) was calculated to be 108 days with a variance of 81. What is the probability that the project will be completed in 110 days or less?