Question: Project Network Homework # 2 : Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely

Project Network Homework #2:
Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely comply with the six rules of AOA while setting up AOA.
\table[[Activity,Duration (Days),Immediate Predecessor(s)],[A,6,None],[B,9,None],[C,8,A,B],[D,7,A,B],[E,10,D],[F,12,C,E]]
(1) There should be q, paths.
(2) Critical length =q, days.
(3) There should be q, non-critical activities.
(4) There should be q, dummy arc(s) in the AOA network.